Standards Australia published Amendment 2 of the Wiring Rules on 30 April 2021. These standards will come into effect on 1st November 2021 for all states* and territories. The amendment covers the following areas:
- Clarifications concerning RCD requirements for alterations
- Clause 2.10.2.2 — switchboard accessibility and emergency exit facilities: location, spacing, room layout, switchboard doors and switchboard room doorways
- Clause 2.10.3.2 — switchboard construction and verification: boards rated at 125 A per phase or 10 kA fault capacity must comply with either AS/NZS 3439 or AS/NZS 61439
- Switchboard type testing and verification requirements clarified
- Figures 7.3 to 7.6 (connection of generator sets to existing fixed electrical installations have been replaced)
- Clause 8.3.7 — Polarity and correct circuit connections: testing requirements
A copy of AS/NZS 3000:2018 and 2:2021 can be purchased from Standards Australia.
(*New South Wales has adopted this since 30th April 2021)